A company that sells a single product would like to decide how many items it should have in inventory for each of the next n months (n is a fixed input parameter). The times between demands are IID exponential random variables with a mean of 0.1 month. The sizes of the demands,D, are IID random variables ……….

inventory.c

/* External definitions for inventory system. */

#include <stdio.h>
#include <stdlib.h>
#include <math.h>
#include “lcgrand.h”  /* Header file for random-number generator. */

int   amount, bigs, initial_inv_level, inv_level, next_event_type, num_events,
num_months, num_values_demand, smalls;
float area_holding, area_shortage, holding_cost, incremental_cost, maxlag,
mean_interdemand, minlag, prob_distrib_demand[26], setup_cost,
shortage_cost, sim_time, time_last_event, time_next_event[5],
total_ordering_cost;
FILE  *infile, *outfile;

void  initialize(void);
void  timing(void);
void  order_arrival(void);
void  demand(void);
void  evaluate(void);
void  report(void);
void  update_time_avg_stats(void);
float expon(float mean);
int   random_integer(float prob_distrib []);
float uniform(float a, float b);

int main()  /* Main function. */
{
int i, num_policies;

/* Open input and output files. */

infile  = fopen(“inv.in”,  “r”);
outfile = fopen(“inv.out”, “w”);

/* Specify the number of events for the timing function. */

num_events = 4;

/* Read input parameters. */

fscanf(infile, “%d %d %d %d %f %f %f %f %f %f %f”,
&initial_inv_level, &num_months, &num_policies, &num_values_demand,
&mean_interdemand, &setup_cost, &incremental_cost, &holding_cost,
&shortage_cost, &minlag, &maxlag);
for (i = 1; i <= num_values_demand; ++i)
fscanf(infile, “%f”, &prob_distrib_demand[i]);

/* Write report heading and input parameters. */

fprintf(outfile, “Single-product inventory system\n\n”);
fprintf(outfile, “Initial inventory level%24d items\n\n”,
initial_inv_level);
fprintf(outfile, “Number of demand sizes%25d\n\n”, num_values_demand);
fprintf(outfile, “Distribution function of demand sizes  “);
for (i = 1; i <= num_values_demand; ++i)
fprintf(outfile, “%8.3f”, prob_distrib_demand[i]);
fprintf(outfile, “\n\nMean interdemand time%26.2f\n\n”, mean_interdemand);
fprintf(outfile, “Delivery lag range%29.2f to%10.2f months\n\n”, minlag,
maxlag);
fprintf(outfile, “Length of the simulation%23d months\n\n”, num_months);
fprintf(outfile, “K =%6.1f   i =%6.1f   h =%6.1f   pi =%6.1f\n\n”,
setup_cost, incremental_cost, holding_cost, shortage_cost);
fprintf(outfile, “Number of policies%29d\n\n”, num_policies);
fprintf(outfile, ”                 Average        Average”);
fprintf(outfile, ”        Average        Average\n”);
fprintf(outfile, ”  Policy       total cost    ordering cost”);
fprintf(outfile, ”  holding cost   shortage cost”);

/* Run the simulation varying the inventory policy. */

for (i = 1; i <= num_policies; ++i) {

/* Read the inventory policy, and initialize the simulation. */

fscanf(infile, “%d %d”, &smalls, &bigs);
initialize();

/* Run the simulation until it terminates after an end-simulation event
(type 3) occurs. */

do {

/* Determine the next event. */

timing();

/* Update time-average statistical accumulators. */

update_time_avg_stats();

/* Invoke the appropriate event function. */

switch (next_event_type) {
case 1:
order_arrival();
break;
case 2:
demand();
break;
case 4:
evaluate();
break;
case 3:
report();
break;
}

/* If the event just executed was not the end-simulation event (type 3),
continue simulating.  Otherwise, end the simulation for the current
(s,S) pair and go on to the next pair (if any). */

} while (next_event_type != 3);
}

/* End the simulations. */

fclose(infile);
fclose(outfile);

return 0;
}

void initialize(void)  /* Initialization function. */
{
/* Initialize the simulation clock. */

sim_time = 0.0;

/* Initialize the state variables. */

inv_level       = initial_inv_level;
time_last_event = 0.0;

/* Initialize the statistical counters. */

total_ordering_cost = 0.0;
area_holding        = 0.0;
area_shortage       = 0.0;

/* Initialize the event list.  Since no order is outstanding, the order-
arrival event is eliminated from consideration. */

time_next_event[1] = 1.0e+30;
time_next_event[2] = sim_time + expon(mean_interdemand);
time_next_event[3] = num_months;
time_next_event[4] = 0.0;
}

void timing(void)  /* Timing function. */
{
int   i;
float min_time_next_event = 1.0e+29;

next_event_type = 0;

/* Determine the event type of the next event to occur. */

for (i = 1; i <= num_events; ++i)
if (time_next_event[i] < min_time_next_event) {
min_time_next_event = time_next_event[i];
next_event_type     = i;
}

/* Check to see whether the event list is empty. */

if (next_event_type == 0) {

/* The event list is empty, so stop the simulation */

fprintf(outfile, “\nEvent list empty at time %f”, sim_time);
exit(1);
}

/* The event list is not empty, so advance the simulation clock. */

sim_time = min_time_next_event;
}

void order_arrival(void)  /* Order arrival event function. */
{
/* Increment the inventory level by the amount ordered. */

inv_level += amount;

/* Since no order is now outstanding, eliminate the order-arrival event from
consideration. */

time_next_event[1] = 1.0e+30;
}

void demand(void)  /* Demand event function. */
{
/* Decrement the inventory level by a generated demand size. */

inv_level -= random_integer(prob_distrib_demand);

/* Schedule the time of the next demand. */

time_next_event[2] = sim_time + expon(mean_interdemand);
}

void evaluate(void)  /* Inventory-evaluation event function. */
{
/* Check whether the inventory level is less than smalls. */

if (inv_level < smalls) {

/* The inventory level is less than smalls, so place an order for the
appropriate amount. */

amount               = bigs – inv_level;
total_ordering_cost += setup_cost + incremental_cost * amount;

/* Schedule the arrival of the order. */

time_next_event[1] = sim_time + uniform(minlag, maxlag);
}

/* Regardless of the place-order decision, schedule the next inventory
evaluation. */

time_next_event[4] = sim_time + 1.0;
}

void report(void)  /* Report generator function. */
{
/* Compute and write estimates of desired measures of performance. */

float avg_holding_cost, avg_ordering_cost, avg_shortage_cost;

avg_ordering_cost = total_ordering_cost / num_months;
avg_holding_cost  = holding_cost * area_holding / num_months;
avg_shortage_cost = shortage_cost * area_shortage / num_months;
fprintf(outfile, “\n\n(%3d,%3d)%15.2f%15.2f%15.2f%15.2f”,
smalls, bigs,
avg_ordering_cost + avg_holding_cost + avg_shortage_cost,
avg_ordering_cost, avg_holding_cost, avg_shortage_cost);
}

void update_time_avg_stats(void)  /* Update area accumulators for time-average
statistics. */
{
float time_since_last_event;

/* Compute time since last event, and update last-event-time marker. */

time_since_last_event = sim_time – time_last_event;
time_last_event       = sim_time;

/* Determine the status of the inventory level during the previous interval.
If the inventory level during the previous interval was negative, update
area_shortage.  If it was positive, update area_holding.  If it was zero,
no update is needed. */

if (inv_level < 0)
area_shortage -= inv_level * time_since_last_event;
else if (inv_level > 0)
area_holding  += inv_level * time_since_last_event;
}

float expon(float mean)  /* Exponential variate generation function. */
{
/* Return an exponential random variate with mean “mean”. */

return -mean * log(lcgrand(1));
}

int random_integer(float prob_distrib[])  /* Random integer generation
function. */
{
int   i;
float u;

/* Generate a U(0,1) random variate. */

u = lcgrand(1);

/* Return a random integer in accordance with the (cumulative) distribution
function prob_distrib. */

for (i = 1; u >= prob_distrib[i]; ++i)
;
return i;
}

float uniform(float a, float b)  /* Uniform variate generation function. */
{
/* Return a U(a,b) random variate. */

return a + lcgrand(1) * (b – a);
}

lcgrand.c and lcgrand.h code can be found here.

inv.in – Input Simulation

input parameters  : Initial inventory level, length of the simulation, number of policies, number of value demand, mean interdemand, setup cost,  incremental cost, holding cost, shortage cost,  delivery lag range and small/big  item have to order.

inv.out – Output Simulation

Reference :
Textbook : Simulation Modeling and Analysis

Copy other researcher’s skills